Club Rooms Upgrade

Castlegregory Community Council is embarking on upgrading the Club rooms in Castlegregory. Read the full report by clicking on this link:-

https://designrr.s3.amazonaws.com/castleinfocenter_at_gmail.com_155214/New%20project%201613138536_6043.pdf

 

 

 

 

06/04/2022

Work is currently in progress on the upgrade. Work on the main hall is nearly completed, The ceiling have been raised , insulation to walls and ceilings is completed. All electrical wiring is in place, Walls and ceiling have been plastered. Flooring is being decided and will be ordered in the next few days.

Is is then planned to proceed to upgrade the toilet facilities with the installation of a disability toilet and revamp of the older toilets again with insulation, new flooring, electrical, painting and baby changing facilities.

19/04/22

Upgrade work to toilet facilities are underway. Painting of large hall will commence in next week followed by laying of new floors.